Five years, millions of dollars: The battle to fix a defective Sydney building

3
0

source : the age

When Andrew and Lisa Cook moved into their new apartment in Baulkham Hills on December 12, 2020, they thought they were getting the dream: a modern unit, a sprawling balcony with views of the city skyline and access to shops at the base of their building.

Just 23 days later, the dream became a nightmare: the company that developed the building collapsed. Ten months after that, the state’s building regulator identified serious defects in the development, including one that was labelled a “hazard to human life”.

The Cooks were shocked. They didn’t know who would be responsible for fixing the defects, and what it meant for their new home. “[We were] a bit scared because they didn’t know what was going to happen at the time,” Lisa said.

Andrew and Lisa Cook on their balcony, which is still being repaired.Jessica Hromas

Known then as the Modena, the four-tower project was developed by Hills Shoppingtown Pty Ltd, a subsidiary of Dyldam Group – once one of NSW’s biggest apartment builders before it collapsed with debts of half a billion dollars.

There were 230 apartments and plans for a retail precinct in a project designed to combine luxury and comfort. When the receivers for the development and the building regulator visited the site, they found it was far from that vision.

In addition to non-compliant waterproofing, an awning in danger of collapse, balconies without water overflows, the glass elevator – designed as a key feature for the project – had already rusted and was leaning slightly.

For five years, the Cooks and a handful of other residents have lived in a construction zone as millions of dollars were funnelled into rectifying defects. The scale of the work is so significant that the Cooks have lived in another unit since January while work on their own apartment continues.

“There’s been a lot of noise for quite a few years, so that’s sort of a bad thing, but I keep thinking they’re doing it, they’re fixing it, it’s not costing us any money,” Andrew said.

The Baulkham Hills building, formerly known as the Modena.
The Baulkham Hills building, formerly known as the Modena.Jessica Hromas.
The stairs to the lower lever remain fenced-off while work continues.
The stairs to the lower lever remain fenced-off while work continues.Jessica Hromas

“We’re one of the fortunate buildings in Sydney.”

Buying a home with defects is not an uncommon experience in NSW. Building Commission NSW ordered major developer Bathla Group, which entered voluntary administration last month, to fix serious defects in two of its developments. It’s left those who purchased off the plan uncertain if they would ever move in.

So when developers collapse owing millions of dollars, how do you fix a defective building?

The $70 million fix

When McGrathNicol was appointed the receiver of the Modena development in 2021, partner Jason Ireland said they were told the project was 95 per cent complete. But what was anticipated to be a quick fix soon became a mammoth project that would take years and $70 million to rectify defects – bringing the total cost of completing the development to $185 million.

Ireland describes the project as being a bit like an onion, “in that when you peeled back [layers], you found more problems that made you cry,” he said. More than 60 defects were found throughout the four buildings.

McGrathNicol’s Jason Ireland said it has cost $70 million dollars to fix the defects left behind by the original builder.
McGrathNicol’s Jason Ireland said it has cost $70 million dollars to fix the defects left behind by the original builder.Jessica Hromas

Fixing the overflow holes in balconies was considered a simple job. Then the tiles began to be removed, and a new problem appeared: No one could identify what waterproofing material had been used. Ireland said it was clear it was a non-compliant product.

“We eventually got to the conclusion that the only way to actually get the sign-off in the end was to rip up the balconies, replace all of the waterproofing, and replace all of the tiling, which is a lot because there’s over 200 apartments,” he said.

Through it all, the four buildings have been partially occupied. In a Tetris-like process, residents had to be moved from their apartments to another in the development to allow for each to be rectified in turn.

When the Herald visited last month, work was continuing. The elevator had been replaced, the stairs to the lower level remained fenced off and some balconies – including the Cooks’ – were still under repair.

The new elevator, which the replaced the original, rusted one.
The new elevator, which the replaced the original, rusted one.Jessica Hromas

Ireland said there is light at the end of the tunnel, with 90 per cent of the defects fixed. Building Commission NSW lifted its building work rectification and prohibition order for the development, which has been rebranded as “Alfresco Quarter”. An interim occupation certificate remains in place.

In May, the commission accepted a voluntary undertaking from McGrathNicol, which will provide additional independent oversight of the development.

About 50 per cent of the apartments have now been sold, and the empty retail precinct has been acquired by property services provider Mintus. The lower level will have a gym, and cafés and restaurants are planned for the upper level. Work will be completed next year.

An artist’s impression of what the cafe at the Baulkham Hills development would look like.
An artist’s impression of what the cafe at the Baulkham Hills development would look like.Alfresco Quarter

Ireland said: “The silver lining to the cloud is that if you buy a property in this building, you know it’s been through the highest of verification standards by the building commissioner’s team. They have been through it with a fine tooth comb.

“Some of the people [living] here have been to hell and back, but importantly, back.”

The lucky ones

It’s been a difficult, drawn-out process for the Cooks, but they’ve remained positive and hope to move back into their own apartment before the end of the year.

“This is our forever home,” Andrew said. “And the tiles they put down are much nicer than the old ones.”

Despite the stress it’s caused, the Cooks consider themselves lucky; unlike many other owners living in buildings with defects built by collapsed developers, the family didn’t have to fund the repairs.

At the Vicinity complex in Canterbury, owners are still picking up the tab after major structural defects were discovered in parts of the 276-apartment complex, which was built by collapsed developer Toplace.

Ellie BusbyEllie Busby is a Parramatta reporter at The Sydney Morning Herald.Connect via X or email.